Smooth Curves
Removed Potholes With Just 145 m3/ha Earthworks
Location: Queensland, Australia
Field Area: 115 ha or 284 acres
Irrigation: Furrow Irrigation
Crops: Sugarcane
Background
This 115 hectare field has scattered pot holes around the field. It needs considerable smoothing to avoid the pot holes but still follow the lay of the land to minimize top soil movement.
Design Inputs
Design Results
Existing Topography
Proposed Topography
Proposed Cut/Fill Map
Long Section (Along Direction of Row)
Cross Section (Across the Row)
Conclusion
An OptiSurface1D design has been calculated to drain water down the field to the southeast direction Following the natural topography of the field. Significant smoothing was applied in the main slope and cross slope directions and maximum grades were limited to 1%. This resulted in smooth design surface with earthworks of 145 m3/ha (76 yd3/acre).